For which type of outline agreement is the material determined from the item category?

Improve your knowledge with our SAP S/4Hana Sales Test. Use flashcards and multiple choice questions for comprehensive preparation. Get ready for success!

The correct answer is the value contract. In the context of SAP S/4HANA, a value contract is used when the customer commits to purchasing a certain monetary value of materials or services over a specified period, but without specifying the exact quantities or delivery dates upfront.

For value contracts, the material is typically determined from the item category during the procurement process. This means that when a value contract is established, the specific materials needed for fulfilling the contract can be dynamically identified based on the item category specified in the contract.

This ability to determine materials from the item category is crucial in scenarios where flexibility is required regarding quantities and types of materials, allowing businesses to manage their procurement activities more effectively. Other types of outline agreements, such as framework agreements, quantity contracts, and service agreements, may involve different structures or requirements that do not focus on the material determination in the same manner.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy